Traffic Advisory for the Week of 10/9/2023 – 10/13/2023

EASTERN KERN, INYO, and MONO COUNTIES – The California Department of Transportation (Caltrans) announces the following project work and traffic impacts for the week of October 2 – October 6.

Work schedules are subject to change due to traffic incidents, weather, availability of equipment and/or materials, and/or construction-related issues.

Inyo County

·      Cartago Traffic Switch – On U.S. 395 north of Cartago, northbound and southbound traffic has switched to temporary lanes north of Cartago. Traffic speeds are reduced to 45 MPH through the current alignment for driver safety. Drivers may experience short delays.

·      State Route 190 Closure – Due to extensive damage from Tropical Storm Hilary, State Route 190 remains closed from the junction with U.S. Highway 395 in Olancha to the junction with State Route 127 in Death Valley Junction.

Mono County

·      Topaz Lake Emergency Repair Project – On U.S. 395 approximately 1.9 miles south of the Nevada State Line, crews are realigning a 0.5-mile stretch of the road to repair winter storm damage Monday through Friday from 7:00 am to 7:00 pm. There is one-way traffic control with a pilot car during work hours and drivers may experience 20-minute delays.

·      CMS Board Construction – On U.S. 395, crews are installing new Changeable Message Signs near Huggans Lane just south of the junction with State Route 182 in Bridgeport. Work is scheduled on Wednesday from 8:00 am to 5:00 pm. There will be one-way traffic control and drivers may experience 5-minute delays.

·      Mono County Utility Work – On U.S. 395 between Green Creek Road and the junction with State Route 270 (Bodie Road), utility crews will replace a pole on Tuesday from 8:30 am to 3:00 pm. There will be one-way traffic control and drivers may experience 10-minute delays.

·      Conway Ranch Shoulders Project – On U.S. 395 between State Route 167 and just north of Conway Ranch Road near Mono City, crews are widening the shoulders, lengthening chain-up areas, installing lighting, and rehabilitating drainage infrastructure. Work is scheduled Monday through Friday from 7:00 am to 6:00 pm. There will be one-way traffic control and drivers may experience 20-minute delays.

·      June Lake Loop Emergency Work – On the northbound lane of State Route 158 (June Lake Loop) between Iowa Street and Silver Lake Campground, there will be emergency work on Monday from 7:00 am to 4:00 pm. Drivers could experience brief delays.

Projects on the state highway system with minimal or no delays:

Eastern Kern County

·      Ridgecrest Sewer Replacement – On State Route 178 E between Gemstone Street and French Avenue, crews continue to replace a sewer line Monday through Friday from 7:00 am to 4:00 pm. Drivers could experience brief delays due to intermittent and turn lane closures.

·      Systemic Pedestrian Safety Improvements – On State Route 202 between Woodford-Tehachapi Road and Tucker Road in the city of Tehachapi, crews are replacing pedestrian crossings, markings, and signs overnight Monday through Thursday from 8:00 pm to 6:00 am.

·      Kern Digouts and Slab Replacement Project – On State Route 58 from just east of the Mill Street overcrossing to Exit 156 near the city of Tehachapi, crews will resume with performing digouts and replacing slabs in the pavement Monday through Friday from 7:00 am to 5:00 pm. One lane will remain open in each direction and drivers may experience short delays.

·      Overnight Mojave Utility Work – On the northbound direction of State Route 14 between the northern junction with Business Route 58 and Arroyo Avenue, there will be overnight utility work on Thursday from 9:00 pm to 7:00 am.

·      Rosamond Xeriscape Project – On State Route 14 at the Rosamond Boulevard overcrossing, crews are nearly finished placing gravel mulch and hydroseeding. Travelers should slow and move over for crew safety.

Inyo County

·      Fort Independence Roadway Widening – On the northbound lanes of U.S. 395 at the intersection with Dusty Lane in Fort Independence, crews are widening the highway and constructing a turn lane Monday through Friday from 7:00 am to 5:00 pm.

·      Whitney Portal Road Detour Sign – On U.S. 395 near the intersection with Lubken Canyon Road, there will be portable message signs informing travelers of a detour for Whitney Portal Road Monday through Friday from 7:00 am to 5:00 pm.

·      Olancha Shoulder Closures – On U.S. 395 at the junction with State Route 190 in Olancha, there will be intermittent shoulder closures to allow trucks access to deliver material Tuesday through Friday from 7:00 am to 5:00 pm.

Mono County

·      Sonora Pass Guardrail Replacement – On State Route 108 between the winter closure gate near the Marine Corps Mountain Training Center and the junction with U.S. 395, guardrail work remains suspended.

·      Cemetery CAPM – On U.S. 395 between Cemetery Road and State Route 167 near Mono City, crews are striping the roadway and installing signs Monday through Friday from 7:00 am to 6:00 pm. There will be intermittent single-lane closures and drivers may experience minimal delays.

·      State Route 203 Sewer Installation – On State Route 203 between Manzanita Road and Old Mammoth Road at Center Street, crews are installing a new sewer line Monday through Friday from 7:00 am and 5:00 pm. Delays will be minimal. Access will be available as the installation progresses across/under the highway. Travel safely through the work zone.

·      U.S. 395 Utility Work – On the southbound on-ramp to State Route 203 at the junction with U.S. 395, shoulder closures will allow utility crews to work Tuesday through Friday from 7:00 am to 5:00 pm.

The Conway Ranch Shoulders Project received $8.3 million from IIJA.

The $3.1 million-Kern Digouts and Slab Replacement Project and $7.4 million-Cemetery CAPM Project are funded by SB 1.

SB 1, the Road Repair and Accountability Act of 2017, provides $5 billion in transportation funding annually split between the state and local agencies. Road projects progress through construction phases more quickly based on the availability of SB 1 funds, including projects that are partially funded by SB 1. For more information about other transportation projects funded by SB 1, visit http://rebuildingca.ca.gov.

Under IIJA, California will receive an estimated $41.9 billion over 5 years. IIJA provides significant funding to Caltrans to improve roadways, bridges, freight projects, public transportation, and safety, and to address climate change. For more information about IIJA, visit http://rebuildingca.ca.gov/iija-by-the-numbers.

Travelers are asked to be attentive to workers on the highway, slow for the cone zone, and move over whenever possible to give additional clearance. Be Safe and Be Work Zone Alert!

Follow us for the latest information on Facebook (Caltrans District 9), Twitter (@Caltrans9), and Instagram (@Caltransd9), or email us at [email protected]. To assist in planning your commute, view live traffic conditions using QuickMap at http://quickmap.dot.ca.gov/.


Discover more from Sierra Wave: Eastern Sierra News - The Communities News

Subscribe to get the latest posts sent to your email.

Discover more from Sierra Wave: Eastern Sierra News - The Communities News

Subscribe now to keep reading and get access to the full archive.

Continue reading